I've been trying to tease out of the delivery tracking master thread the actual time it takes to get the car from build date, and trying to remember from when my 335 was built. Here's what I've been adding up for myself in the midwest based on the info provided previously:

Build start (150) to build finish (155): 1-2 weeks.
-Build finish (155) to Scheduled for Carrier (182): 1 day.
-Status 182 to 190 (on a train to bremerhaven):1-3 days.
-Status 190 to 193 (at port awaiting a ship): 1-2 days.
-Status 193 to 195 (on a ship): 3-5 days for east coast delivery,
-Shipping time from Bremerhaven to East Coast: 12-17 days depending on the number of stops.
--Offload at port: 1 day
-Processing through customs: 1-2 days
-Process through BMW Vehicle Processing Center (VPC) and onto a carrier: 2-5 days.
-Shipping time on carrier to Dealership: 1-4 days.

So on the long side - ~54 days/8 weeks) and short side ~30 days/4 weeks.

I've been mentally assuming about 6 weeks from build start, so if Week 41, then in my hands week of November 16th.

(Found my original build sheet/production number on my 335 and it was almost exactly 8 weeks from status 112 to in my hands)